ONGOING PROJECTS
PROJECT IN PIERA
Land Clearing, February 2025
Excavation, February 2025
Earthworks, February 2025
Soil Removal, March 2025
Formwork Preparation, March 2025
Concrete Pouring, April 2025
Wall Construction Preparation, April 2025
Closing the Parking and Basement, April 2025
Concrete Pouring for Structural Preparation, May 2025
Steel Frame Installation, June 2025
Front Cladding, July 2025
Rear Cladding, July 2025
Leveling the Ground for Pool Formwork, July 2025
PROJECT IN CAMBRILS
Initial land, February 2025
Preparation for start of construction, March 2025
Excavations, March 2025
Earthworks, March 2025
Formwork preparation, March 2025
Preparation for foundation concrete, March 2025
Footing concreting, April 2025
Foundation concreting, April 2025
Preparation for Steel Frame installation, April 2025
Steel Frame Installation, April 2025
Steel Frame, April 2025
Steel Frame, May 2025
OSB Installation, May 2025
OSB Wall Cladding, May 2025
OSB Wall Cladding, May 2025
OSB Wall Cladding, June 2025
Roof Installation, July 2025
Front Cladding, July 2025
Pladur Installation, July 2025
Pending Rear Cladding, July 2025
PROJECT IN CASTELLVI
Earthworks, December 2024
Foundation preparation, December 2024
Pouring foundation concrete, December 2024
Pipe preparation, December 2024
Foundation preparation, December 2024
Foundation preparation, December 2024
Pouring concrete for foundation, December 2024
Structure installation, December 2024
Pool formwork preparation, December 2024
Exterior membrane cladding, January 2025
Concrete pool, January 2025
OSB cladding, January 2025
OSB cladding, January 2025
Placement of the exterior membrane, January 2025
Installation of doors and windows, February 2025
Installation of steps in the pool, February 2025
Exterior walls, April 2025
PROJECT IN MOLINS DE REY
PROJECT IN CERVELLO
PROJECT IN REUS
Marking, February 2025
Steel Frame Installation, February 2025
OSB Installation, February 2025
Window and False Ceiling Installation, March 2025
Door Installation, March 2025
Kitchen Tile Installation, March 2025
Exterior Wall Installation, April 2025
Final Finishes, June 2025
Kitchen Installation, July 2025